Peaty ground- made for mass stabilization
|
|
- Rolf Strömberg
- för 8 år sedan
- Visningar:
Transkript
1 NGM 2016 Reykjavik Proceedings of the 17 th Nordic Geotechnical Meeting Challenges in Nordic Geotechnic 25 th 28 th of May Peaty ground- made for mass stabilization Madelene Markusson. WSP Sverige AB, SWEDEN, ABSTRACT Roslagsbanan is a narrow gauge railway in the northeast region of Stockholm. The railway was built in the early 1900s. WSP has produced construction documents for the part Rydbo-Åkers Runö and the construction of this part took place in the year 2013 and The part was divided in three segments. In the second segment there is an area called Täljö station were mass stabilization was used as ground reinforcement. Soil layers at Täljö station generally consist of an upper layer of peat and mud with a thickness of up to 4 m resting on soft clay down to at most 15 meters below the ground surface. The area has previously had problems with settlements and in 2007 tracks adjustment and reinforcement through mass stabilization of peat layer of the existing track was done. Mass stabilization is a fast and cost effective method for hardening the loose soil layers by adding binding agents. With this method the entrepreneur do not have to transport poor masses to landfill and refill with qualified filling. This saves time, money, and is a gentle metod for reinforcement from an environmental perspective since existing soil layer is used on-site (in-situ) so that transport and thermal ballast are minimized. Another advantage of mass stabilization is that the working area size can often be reduced since the excavation of the slope can be avoided. Based on the good experience from previous stabilization works mass stabilization in combination with lime cement columns in the claylayer were also selected for the new renovation and construction of a new track. Work on Roslagsbanan is a good example of how mass stabilization effectively can be used to reinforce organic soils and cohesive soils under road- and railway embankments. Keywords: Masstabilisering, kalkcementpelare, torv, peat, järnväg 1 BAKGRUND Roslagsbanan är en smalspårig järnväg från början av 1900-talet. Roslagsbanan trafikerar Stockholms nordöstra förorter och denna artikel behandlar främst Täljö station på sträckan Rydbo-Åkers Runö. Bansträckningen går genom fastmarkspartier men korsar däremellan gamla havsvikar med organisk jord och sediment av lera. Banan byggdes genom utläggning av trärustbädd men var i övrigt oförstärkt. När banan skulle färdigställas försenades invigningen på grund av skred i järnvägsbanken, dock ej på aktuell sträcka. Järnvägsbanken har sedan erhållit sättningar som på vissa avsnitt uppgår till ca 1 meter. 2 PROJEKTERING AV UPPRUSTNING STRÄCKAN VIGGBYHOLM- ÖSTERSKÄR År 2007 projekterade WSP Sverige AB, på uppdrag av Stockholms Lokaltrafik (SL), en upprustning av sträckan mellan Viggbyholm och Österskär. Upprustningen innebar bla att masstabilisering utfördes som förstärkningsåtgärd på en sträcka av ca 500 meter på delsträckan Rydbo- Åkers Runö. En stor del av problemsträckan låg vid Täljö station. Här passerar banan flera områden där jordlagren består av torv och gyttja med underliggande lager av lera vilket med årens lopp inneburit problem med både stabilitet och sättningar vilket resulterat i att regelbundna spårjusteringar erfordrats. Då upprustning av banan beslutades, vilket innebar ökad standard genom att tex betongslipers och helsvetsade räler anlades, fanns mindre tolerans för regelbundna justeringar. IGS 905 NGM Proceedings
2 Geotechnical structures and infrastructure Vid Täljö station förelåg problem med att plattformselementen satt sig och stationen planerades att rivas. Sonderingar genom befintlig bank, utförda år 2007, visade på att banken satt sig mellan 0,5 till 2 meter i den organiska jorden. Upprustningen innebar att den gamla banken ersattes med en ny bank och masstabilisering utfördes under den nya bankens hela bredd. Därefter skulle en temporär stationen byggas upp igen. Figur 1 Kartbild hämtad från google maps. Aktuellt område är inringat med rött. 3 GEOTEKNISKA FÖRHÅLLANDEN VID TÄLJÖ STATION 3.1 Terräng Järnvägsträckningen går över kärrmark mellan ca km till Marknivån över den skogsbevuxna kärrmarken är ca + 24,5 till +25 mellan och och ca +22 på resterande sträcka, med små variationer. 3.2 Jordlagerbeskrivning I läget för befintlig järnväg finns överst någon till ett par meter fyllning. Där marken är orörd består jordlagren överst av 1 à 4 meter torv och gyttja. Därunder finns lera som vilar på friktionsjord på berg. Djupet till fasta jordlager eller berg varierar mellan ca 5 till 15 meter. Torven är i allmänhet medeltill högförmultnad. De övre delarna av leran är gyttjig. Torven och gyttjan har vid sidan av järnvägsbanken en korrigerad odränerad skjuvhållfasthet som är ca 4 kpa ner till 4 meters djup från markytan. Lerans korrigerade odränerade skjuvhållfasthet bedöms vara 5 kpa på 4 meters djup från markytan, med en ökning av 1,5 kpa/meter mot djupet därunder. Leran är mellan- till högsensitiv med värden mellan 8 och 63 och under ca 12 meter djup klassificeras leran som kvick. Torvens och gyttjans densitet är ca 1,2 t/m 3. Leran har en densiteten på mellan ca 1,4 och 1,7 t/m 3 där NGM Proceedings 906 IGS
3 Peaty ground-made for mass stabilization de lägre densiteten på leran gäller den övre gyttjiga leran. Den naturliga vattenkvoten (w N ) i torven och gyttjan varierar mellan ca 100 och 550 % och konflytgränsen (w L ) varierar mellan ca 100 till 500 %. Lerans naturliga vattenkvot variera mellan ca 60 till 80 % och konflytgränsen varierar mellan ca 40 och 60 %. Leran bedöms vara överkonsoliderad med ca kpa (OCR ca 1,7) under banken. Kompressionsmodulen M L är låg. I torven och gyttjan bedöms M L vara ca 130 kpa och i leran ca kpa. 3.3 Hydrogeologiska förhållanden Enligt utförda grundvattenmätningar ligger grundvattentrycket i friktionsjorden under leran något över markytenivån. 4 MOTIV TILL VALD FÖRSTÄKNINGSMETOD Olika åtgärdsmetoder övervägdes såsom förstärkning genom KC-pelare eller påldäck, eller urskiftning av torv- och lerjordar. Valet av masstabilisering motiverades med att metoden bidrar till en miljömässig nytta genom att befintliga massor nyttjas på plats (in-situ) så transporter och tillförd ballast kan minimeras. Masstabilisering bedömdes även vara en snabb och kostnadseffektiv metod att hantera sättningsproblematiken samt att det var ur största vikt för SL att snabbt kunna ta järnvägen i bruk igen. 5 FÖRUNDERSÖKNING OCH GENOMFÖRANDE AV MASSTABILISERADE PROVYTOR 5.1 Provytor Vald förstärkningsmetod blev masstabilisering genom inblandning av cement och granulerad masugnslagg (Merrit 5000) i den organiska jorden. För att säkerställa antagandena vid projekteringen och optimera inbladningen av blandningar utfördes provinbladningar på en provyta intill planerad förstärkning. Det beslutades att ett område närmast Täljö station var bäst lämpad. Provytan var ca 20 x 5 meter och 4 st inblandningar användes vilket innebar att provytan delades in i 5x5 meter stora rutor. Följande fyra provinbladningar provades I 200 kg/m 3 och 70/30 (cement/ merit) med extra vatten vid utförandet II 200 kg/m 3 och 70/30 (cement/ merit) utan extra vatten vid utförandet III 250 kg/m 3 och 70/30 (cement/ merit) utan extra vatten vid utförandet IV 250 kg/m 3 och 70/30 (cement/ merit) utan extra vatten vid utförandet, fyllnadshöjd det dubbla strax intill stabilisering. Provytorna fylldes upp med 0,5 meter fyllning ovan en geotextil strax efter utförd stabilisering utom för provyta nr IV där 1 meter fyllning lades ut ovan geotextilen efter stabilisering. Två peglar installerades mitt på varje provyta. Peglarna installerades på geotextilen innan fyllningen lades ut. Efter 7 dygn lades ytterligare 0,5 meter fyllning upp på ytorna I till III. Strax innan stabiliseringen genomfördes luckrades jorden upp av en traktorgrävare. Stabiliseringen genomfördes med trumverktyg. 5.2 Provning Provning genomfördes genom kärnprovtagning med S-Geoborr med en kärndiameter av 102 mm och ytterdiameter av 158 mm. Ett kärnborrhål utfördes på varje yta och 3 till 4 delar av kärnan provtrycktes på SGI s laboratorium i Linköping. Ett par KPS- sonderingar med vinge utfördes på alla ytor utom yta IV där endast sondering kunde genomföras pga den stabiliserade ytans höga fasthet. Pelarvingborr gick endast att genomföra i yta I då den stabiliserade jorden i övriga ytor var för fast. Provning utfördes 1 vecka, 2 veckor samt 5 till 6 veckor efter stabiliseringen. 5.3 Utvärdering av provningen Den stabiliserade massan var inte homogen och fastheten varierade både mot djupet och i i sidled. Eftersom provningen utförts med olika metoder som provar olika stora volymer samt bedöms ha olika noggrannhet vid utvärdering av den stabiliserade jordens IGS 907 NGM Proceedings
4 Geotechnical structures and infrastructure skjuvhållfasthet gjordes en subjektiv viktning av resultaten med avseende på metodernas noggrannhet och metod vid utvärdering. Kärnprovtagning viktades högst (7/10) och sondering med 50 mm spets respektive CPTsondering viktades lägst (2/10). Generellt tenderade utvärderingen av skjuvhållfastheten med tryckförsök i laboratorium ge ett lägre värde än vid utvärdering av sonderingar. Efter 1 till 2 veckor var bindemedlet fortfarande varmt vilket betyder att bindemedlet fortfarande brinner och hållfastheten ökar med tiden. Däremot efter 5 till 6 veckor hade bindemedlet svalnat betydligt. Någon markant förändring av skjuvhållfastheten med tiden noterades dock inte. Slutsatsen var att detta berodde på att provomfattningen var för lite samt att massan var för inhomogen för att kunna göra denna bedömning. Nedanstående tabell redovisar en subjektiv bedömning av skjuvhållfastheten för respektive delyta med bedömda min- och maxvärden i den stabiliserade volymen. Tabell 1 Sammanställning utvärderad odränerad skjuvhållfasthet. Provyta Min Medel Max (kpa) (kpa) (kpa) I (200 kg/m 3 ) II (200 kg/m 3 ) III (250 kg/m 3 ) IV (250 kg/m 3 ) Projekteringen baserades på att skjuvhållfastheten i den masstabiliserade jorden skulle vara minst 50 kpa i hela det stabiliserade blocket och ett snittvärde som borde överstiga 100 kpa vilket samtliga provytor motsvarade. Någon effekt av tillsatt vatten för provyta I kunde inte skönjas. Det är dock viktigt att torven som har sämst egenskaper vid stabilisering blandas med den underliggande gyttjan och leran. Med ledning av den utförda provningen valdes mängden 200 kg/m 3 och blandningen 70% cement och 30% Merrit Uppföljning av sättningsmätning I provytorna Under provningsperioden, dvs ca 6 veckor, har 5 stycken avvägningar av markpeglar utförts. Måttliga rörelser på mellan 0 till 4 cm har uppkommit vid belastning av provytorna. Den provyta som satts sig mest är yta 4 som bedöms ha fått den högsta skjuvhållfastheten och den bästa stabiliserande effekten. 6 GENOMFÖRANDE AV UPPRUSTNINGEN AV BANAN Åtgärderna för upprustningen utfördes under trafikavstängning varför tillgänglig tid för genomförandet var begränsad. Vald inblandningsmängd blev mängden 200 kg/m 3 och blandningen 70% cement och 30% Merrit Förstärkningen genomfördes därefter genom att den befintliga bankroppen samt även överbyggnadsmaterial schaktades bort. Arbetet utfördes succesivt i etapper om ca 5 meter/dag med efterföljande utläggning av underballast efter att den stabiliserade ytan härdat. Arbetena försvårades av att inblandningsverktyget stötte på hinder i form av rustbädd av trästockar. I vissa fall utfördes förschaktning för att rensa bort rustbädden. Efter stabiliseringen påfördes en temporär överlast för att komprimera den stabiliserade jorden. Överlasten lades 1 meter över planerad markyta och med en liggtid av 2 till 4 veckor. Pga den korta tid som överlasten kunde ligga bedömdes att kvarvarande krypdeformationer kan förekomma. Figur2 Principskiss masstabilisering NGM Proceedings 908 IGS
5 Peaty ground-made for mass stabilization 7 PROJEKTERING AV SYSTEMHANDLING ÅR 2010 AV STRÄCKAN RYDBO-ÅKERS RUNÖ År 2010 fick WSP i uppdrag av SL att upprätta en systemhandling för sträckan Rydbo- Åkers Runö där Roslagsbanan föreslog byggas ut till dubbelspår. Vid Täljö station innebar projekteringen av nytt dubbelspår att nytt spår skulle förläggas på södra sidan utmed befintligt spåret med ett spåravstånd på 9 meter med samma profilnivå. Anläggningen och de åtgärder som planerades skulle också förbereda för en framtida övergång till normal spårvidd med tillhörande ökning av trafiklasten (STAX 22,5 ton). Befintlig temporär plattform norr om befintligt spår skulle rivas och ny mittplattform skulle anläggas. I samband med framtagandet av systemhandlingen var det av stort intresse att göra en ny utvärdering av utförda förstärkningar eftersom det planerades att utföra liknande förstärkningar i samband med dubbelspårsutbyggnaden. Därför utfördes ytterligare sättningsuppföljning. Den tidigare stabiliserade sträckan var ca 10 till 15 meter bred och stabilisering hade utförts till fasta jordlager eller till som mest 4 meters djup. Förstärkningsarbetena hade utförts sommaren 2007 samt sommaren Sättningsuppföljning Sättningsmätningar hade pågått under perioden till dvs under drygt 3 år efter att järnvägens överbyggnad var iordningställd. Mätningar hade utförts på slipers i spårmitt med ett c/c avstånd av 20 meter. 7.2 Resultat sättningsuppföljning Efter analys av sättningsmätningarna syntes det tydligt att de större sättningarna hade utbildats inom områden där det underliggande oförstärkta lerlagrets mäktighet ökade. ca 0,5 till 3 cm. Sättningarna bedömdes ha avklingat. Sträckan till På denna sträcka installerades 8 st mätpunkter. Totalsättningen varierade mellan ca 1 till 11,5 cm. Sättningarna hade utbildats relativt jämt över sträckan förutom mellan km och där en sättningsdifferens på ca 8,5 cm uppmätts vilket därmed ej uppfyllde de krav på differenssättningar i längsled som ställts. För sträckan till bedömdes sättningarna ha avklingat. För resterande del mellan km och bedömdes sättningarna inte ha avklingat. Här uppskattades sättningshastigheten till 3 cm/år. Det gjordes en bedömning att sättningarna skulle fortsätta utbildas i den oförstärkta leran under den masstabiliserade torven. 7.3 Konsekvenser för föreslagen utbyggnad till dubbelspår Nya Täljö station planerades att byggas med spåravstånd 6 meter samt mittplattform på sträckan fram till km Detta innebar höga sättningskrav (max 1 cm mellan spår och plattform. Eftersom mätningarna visade på att sättningarna avklingat på denna sträckan bedömdes förutsättningarna som goda för förstärkning av kommande dubbelspår på liknande sätt som utförts för upprustningen. För sträckan till visade mätningarna att det fanns risk för att sättningarna under det nya dubbelspåret inte skulle kunna uppfylla ställda krav om förstärkningen utfördes på liknande sätt som för upprustningen. Man rekommenderade därför i systemhandlingskedet att förstärka det nya spåret med KC-pelare alternativt lastkompensation med lättfyllning på hela eller delar av sträckan. Sträckan till På denna sträcka installerades 7 st mätpunkter. Totalsättningen varierade mellan IGS 909 NGM Proceedings
6 Geotechnical structures and infrastructure 8 PROJEKTERING AV BYGGHANDLING AV STRÄCKAN RYDBO-ÅKERS RUNÖ 8.1 Ytterligare uppföljning av pågående sättningar fram tom juli Tidigt i projektering togs beslut om att ytterligare sättningsmätningar skulle utföras mellan december 2010 till juli Figur 3 Sättningutveckling på aktuell sträcka sedan spårupprustningen, perioden 2007 tom juli 2011 Sättningsuppföljning för befintlig masstabilisering visar att banken har satt sig mellan 1 och 11,5 cm. Sättningarna under nytt spår bedöms bli större eftersom marken här är obelastad sedan tidigare samt att inom viss del av sträckan så är lerdjupet större än under tidigare utförd masstabilisering. 8.2 Föreslagen förstärkning Av denna anledning föreslogs masstabilisering i kombination med KCpelare med en diameter av 60 cm med ett c/cavstånd på 1,4 m i leran. Utförda beräkningar av framtida sättningar i KC-pelarblocket visar en sättning om ca 0,07 m som till största delen skulle utbildas inom 6 månader. Figur 4 Principsektion masstabilisering med KC-pelare 8.3 Kontrollprogram För att kontrollera rörelser i samband med entreprenadarbetena samt följa upp NGM Proceedings 910 IGS
7 Peaty ground-made for mass stabilization förstärkningsåtgärdernas funktion togs ett kontrollprogram fram. Detta omfattade etablering och mätning av ett antal kontroll sektioner. Dessutom föreskrevs sättningsuppföljning med hjälp av krönpeglar var 20:e meter som installerades höger 5,5 meter och höger 11 meter. Kontroll av krönpeglar skulle utföras vid uppfyllning ca halva bankhöjden samt omedelbart efter avslutad uppfyllning av banken. Därefter 1, 2, 4, 8, 16, 24, 36, 52 veckor efter full uppfyllning av banken. Enligt kontrollprogrammet skulle även en inklinometer och en slangsättningsmätare installeras i km Då bindemedelsvagnen måste fyllas på flera gånger om dagen och uppfyllning tar tid så användes två bindelsvagnar. Figur 6 Inblandningsverktyg (Foto: Keller Grundläggning) Figur 5 Principskiss krönpegel 9 UTFÖRANDE Arbetet pågick fram tom sommaren Trafiken släpptes på under hösten Veidekke var huvudentreprenör vid Täljö station och Keller var underentreprenör och ansvarig för masstabiliseringen och KCpelarförstärkningen. Första steget i utförandet var att Veidekke demonterade spår och frigjorde ytorna som skulle stabiliseras samt byggde arbetsvägar på ömse sidor om området som skulle stabiliseras. Efter det installerades KC pelare över hela ytan upp till 0,5 meter över den nivå som utförda undersökningar visade på att torvlagret underkant låg på. Detta för att få god kontakt med masstabiliseringen. När KC pelarna installerats kunde masstabiliseringen ta vid. Utrustningen utgörs av en grävmaskin med ett blandningsverktyg se bild nedan, samt bindemedelsvagn med kompressor. Figur 7 Masstabilisering med bindemedelsvagn (Foto: Keller Grundläggning) 9.1 Uppföljning i byggskedet Några mätvärden från slangsättningsmätare har ej erhållits. Installerad inklinometer vid km visar ej på några avvikelser i rörelserna. Mätvärden från markpeglar har erhållits för perioden 5 maj tom 15 maj 2014 på en del av sträckan mellan km till Mätresultatet visar på rörelser på upp till 10 mm. Enligt spårmätning utförd hösten 2014 ligger nedspåret, dvs det nya spåret upp till 4,9 cm lägre i z-led än de projekterade höjderna. Störst avvikelse är det på sträckan där lerdjupet är som störst mellan km till Enligt samma mätningar ligger uppspår, det befintliga spåret upp till 3,4 cm lägre än projekterade höjder på samma delsträcka. IGS 911 NGM Proceedings
8 Geotechnical structures and infrastructure 11 REFERENSER Nilsson Gunnar (2007), Utvärdering av masstabiliserade provytor, upprustning av Roslagsbanan Täljö station , WSP. Friberg Per (2010), Sätninguppföljning för masstabiliserade ytan mellan ; , WSP Bygghandling Roslagsbanan, Rybo-Åkers Runö (2013), WSP Figur 8 Masstabilisering (Foto: Keller Grundläggning) 10 SLUTSATSER Då förstärkning med enbart masstabilisering i torv utfördes, blev resultatet ur sättningssynpunkt ej tillfredställande. Då byggnation av dubbelspår utfördes och metoden med masstabilisering tillsammans med KC-pelare valdes blev resultatet att utbildade sättningarna blev betydligt mindre. En erfarenhet är att det är viktigt att uppföljning utförs enligt föreslaget kontrollprogram och att mätresultaten dokumenteras och sammanställs. Det blir annars svårt att följa upp om sättningarna blev som utförda beräkningar förutspådde. I detta projekt finns brister i uppföljning och dokumentation vilket försvårat analysen av förstärkningens resultat. Masstabilisering tillsammans med KC-pelare var för detta projekt en snabb och smidig förstärkningsåtgärd då både tidsaspekten och miljöaspekten vägde tungt. NGM Proceedings 912 IGS
Comparison between field monitoring and calculated settlement for railway embankment built on peat
NGM 2016 Reykjavik Proceedings of the 17 th Nordic Geotechnical Meeting Challenges in Nordic Geotechnic 25 th 28 th of May Comparison between field monitoring and calculated settlement for railway embankment
Delområde bebyggelse Söderhamn
SÖDERHAMNS KOMMUN Delområde bebyggelse Söderhamn PM Geoteknik för detaljplan 2018-10-23 1 10272962 Delområde bebyggelse Söderhamn DELOMRÅDE BEBYGGELSE SÖDERHAMN PM Geoteknik för detaljplan KUND Söderhamns
Vegastaden Dpl 2 Haninge kommun
Vegastaden Dpl 2 Haninge kommun Geoteknisk undersökning PM Geoteknik Stockholm 2008-01-21 Uppdragsnummer: 215668 Stephan Hellgren Tyréns AB Vegastaden Dpl 2 PM GEOTEKNIK 2 (8) Stephan Hellgren 08-566 41
Del av fastigheterna Bua 4:94, Bua 10:108 och Bua 10:248
Varbergs Kommun Del av fastigheterna Bua 4:94, Bua 10:108 och Bua 10:248 Ändrad detaljplan Geoteknisk PM 2014-11-28 ÅF-Infrastructure AB Grafiska vägen 2 A, Box 1551 SE-401 51 Göteborg Telefon +46 10 505
RAPPORT KARLSTADS KOMMUN KARLSTAD, JAKOBSBERGSOMRÅDET FYLLNING OCH MASSHANTERING UPPDRAGSNUMMER FÖRSTUDIE
KARLSTADS KOMMUN UPPDRAGSNUMMER 12703132 KARLSTAD, JAKOBSBERGSOMRÅDET FYLLNING OCH MASSHANTERING Sweco Innehållsförteckning 1 Uppdrag 1 2 Befintliga förhållanden 1 3 Planerad bebyggelse 1 4 Tidigare utförda
Tekniskt PM angående geoteknik undersökning för upprättande av detaljplan för nybyggnation av bostäder
PM Skanska Sverige AB Handläggare Cecilia Edmark Datum 2009-12-15 Vår referens/nr 131466.030 DEL AV HJÄLTSGÅRD 6:1, SKEE STRÖMSTAD KOMMUN Tekniskt PM angående geoteknik undersökning för upprättande av
KARLSSONS ÄNG, KALMAR Detaljplan. Översiktlig geoteknisk utredning
KARLSSONS ÄNG, KALMAR 2016-09-02 Upprättad av: Daniel Elm Granskad av: Göran Sätterström Godkänd av: Daniel Elm KUND Kalmar kommun Kommunledningskontoret Projekt- och exploateringsenheten Klara Johansson
Södra Infarten Halmstad Vägutredning
Södra Infarten Halmstad Vägutredning PM Geoteknik 2004-03-15 Region Väst Geoteknik Handläggare: Gunilla Franzén Bitr handläggare: Annika Andréasson Antal sidor: 9 Utskriven: 2005-05-09 Säte i Stockholm
Kungsbacka, Aranäs sporthall, Detaljplan
Kungsbacka kommun Kungsbacka, Aranäs sporthall, Detaljplan Uppdragsnr: 106 04 63 Version: 1.1 1 Uppdragsgivare: Uppdragsgivarens kontaktperson: Konsult: Uppdragsledare: Handläggare: Kungsbacka kommun Ida
OBJEKTSPECIFIK TEKNISK BESKRIVNING VÄG, GEOTEKNIK OTBv/geo
Kontraktshandling 11.4 Förfrågningshandling 11.4 Revideringar under anbudstiden Rev.datum Avsnitt Sida nr VÄG 44 TORP - UDDEVALLA DELEN TAVLEGATAN - FRÖLANDSVÄGENS VÄSTRA GÖTALANDS LÄN OBJEKTNR 428257
Fjällbacka 187:44 och 187:47 Geoteknisk undersökning PM Geoteknik
Sweco Infrastructure AB Geoteknik, Göteborg; 2010-01-05 10:46 Göteborg Sweco Infrastructure AB Geoteknik, Göteborg Uppdragsnummer 2305 389 Sweco Gullbergs Strandgata 3 Box 2203, 403 14 Göteborg Telefon
Lilla Sältan. Projekterings-PM/Geoteknik. Uddevalla Detaljplan BOHUSGEO AB. Uppdragsansvarig: Henrik Lundström. Handläggare: Henrik Lundström
BOHUSGEO AB Uddevalla Detaljplan Projekterings- Uppdragsansvarig: Henrik Lundström Handläggare: Granskning: Henrik Lundström Daniel Lindberg Uppdragsnr. 16072 Datum 2016-07-01 Revision Bohusgeo AB Tel.
Geoteknisk PM Detaljplan
Geoteknisk PM Detaljplan Detaljplan Björnmossevägen Södra, Kälvesta, Stockholms Kommun Projekt nr: 18 13 80 2018-12-19 Geoteknisk PM Detaljplan Detaljplan Björnmossevägen Södra, Kälvesta, Stockholms Kommun
PM GEOTEKNIK TÅSTORP 7:7 M.FL FALKÖPINGS KOMMUN JÖNKÖPING GEOTEKNIK SWECO CIVIL ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING INFÖR DETALJPLAN
FALKÖPINGS KOMMUN UPPDRAGSNUMMER 2204112000 ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING INFÖR DETALJPLAN 2014-04-25 JÖNKÖPING GEOTEKNIK UPRÄTTAD AV: GRANSKAD AV: SWECO CIVIL JOSEFINE LINDBERG BJÖRN PETTERSSON
Hantering av förorenade sediment och muddermassor
Hantering av förorenade sediment och muddermassor -Masstabilisering - geotekniska synpunkter Mikko Leppänen / Ramboll Finland Oy Princip för masstabilisering Masstabilisering erfarenheter sedan 1993 Veittostensuo
Geoteknisk PM Detaljplan
Geoteknisk PM Detaljplan Grästorp 14:1 Grästorp, Grästorp kommun Projekt nr: 18 11 59 2018-07-06 Geoteknisk PM Detaljplan Grästorp 14:1 Grästorp, Grästorp kommun Projekt nr: 18 11 59 Beställare Beställares
E6 Kungälvsmotet (Öst)
VÄGPLAN GRANSKNINGSHANDLING E6 Kungälvsmotet (Öst) Kungälvs kommun, Västra Götalands län PM Geoteknik 2014-07-04 Projektnummer: 102131 1 Dokumenttitel: Granskningshandling E6 Kungälvsmotet (Öst) Dokumentdatum:
Översiktlig geoteknisk utredning för detaljplan vid Björkängen, Torsby kommun Värmlands län
1 (5) Översiktlig geoteknisk utredning för detaljplan vid Björkängen, Torsby kommun Värmlands län Geoteknik Upprättad: EQC Karlstad AB Lagergrens gata 8, 652 26 Karlstad Vxl: 010-440 57 00 www.eqcgroup.se
ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING
Datum Uppdragsnummer 2016-11-21 16 416 REV.2016-12-05 VÄSTERÅS KOMMUN VÄSTERÅS SÖDRA KÄLLTORP BOSTADSOMRÅDE ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING VÄSTERÅS SÖDRA KÄLLTORP BOSTADSOMRÅDE ÖVERSIKTLIG GEOTEKNISK
Väg 161 Delen Bäcken - Rotviksbro
VÄGPLAN Väg 161 Delen Bäcken - Rotviksbro Jämförelse av förstärkningsåtgärder öster om ravinen, km 2/670 2/800 Uddevalla kommun, Västra Götalands län, Geoteknik Objektnummer: 102225, Geoteknik 2 (16) INNEHÅLLSFÖRTECKNING
Borgviks hamnområde, Grums kommun
Datum 2017-03-24 Uppdragsnr 731844 Borgviks hamnområde, Grums kommun PM Geoteknik för detaljplan ÅF-INFRASTRUCTURE AB Helena Kernell GRANSKARE Per Axelsson INNEHÅLL 1. Objekt... 3 2. Syfte och begränsningar...
Stora Sköndal Konsekvensbeskrivning Geoteknik
Handläggare Mikael Johansson Tel 010-505 04 42 Mobil 072-219 15 48 E-post mikael.a.johansson@afconsult.com Datum 2016-12-05 Rev 2019-03-12 Projekt-ID 719324 Kund Stiftelsen Stora Sköndal Stora Sköndal
PM GEOTEKNIK. Norrtälje hamn, Norrtälje. Småbåtshamn, Tälje s:30. Översiktlig geoteknisk utredning. ÅF-Infrastructure AB. Axel Lehmann Handläggare
Author Axel Lehmann Phone +46 10 505 15 28 Date 2016-03-24 Project ID 713028 E-mail axel.lehmann@afconsult.com Client Norrtälje kommun Norrtälje hamn, Norrtälje Småbåtshamn, Tälje s:30 Översiktlig geoteknisk
Detaljplan del av Duvehed, Fjärås Kungsbacka kommun Geoteknisk utredning
Detaljplan del av Duvehed, Fjärås Detaljplan del av Duvehed, Fjärås Beställare: KUNGSBACKA KOMMUN 43481 KUNGSBACKA Beställarens representant: Rolf Enskog/Inger Gennerud Konsult: Uppdragsledare Norconsult
ALINGSÅKER ETAPP 1, TROLLHÄTTAN
OKTOBER 2017 TROLLHÄTTANS STAD ALINGSÅKER ETAPP 1, TROLLHÄTTAN ADRESS COWI AB Skärgårdsgatan 1 Box 12076 402 41 Göteborg TEL 010 850 10 00 FAX 010 850 10 10 WWW cowi.se OKTOBER 2017 TROLLHÄTTANS STAD
PLANERINGSUNDERLAG SJUKHUSKVARTERET 18 OCH 19, LANDSKRONA, FASTIGHETSBOLAGET KRONAN 2 LANDSKRONA AB UPPRÄTTAD:
PLANERINGSUNDERLAG SJUKHUSKVARTERET 18 OCH 19, LANDSKRONA, FASTIGHETSBOLAGET KRONAN 2 LANDSKRONA AB UPPRÄTTAD: Upprättad av Granskad av Godkänd av Elisabeth Lindvall Fredrik Griwell Fredrik Griwell Innehållsförteckning
Kv Porfyren 2. Projekterings-PM/Geoteknik. Kartåsen, Lidköping Detaljplan BOHUSGEO AB. Uppdragsansvarig: Henrik Lundström.
BOHUSGEO AB Kv Porfyren 2 Kartåsen, Lidköping Detaljplan Projekterings- Uppdragsansvarig: Henrik Lundström Handläggare: Granskning: Henrik Lundström Mats Falck Uppdragsnr. 15126 Datum 2016-01-05 Revision
Kungsbacka. Detaljplan för del av Åsa 3:303 & 3:205. Geoteknisk utredning för detaljplan
Kungsbacka. Detaljplan för del av Åsa 3:303 & 3:205. Beställare: Kungsbacka Kommun 434 81 Kungsbacka Beställarens representant: Jonas Alborn Konsult: Uppdragsledare Handläggare Norconsult AB Box 8774 402
PLANERINGS PM/GEOTEKNIK
SAMHÄLLSBYGGNADSKONTORET, VARBERGS KOMMUN Östra Kvarngården, Varberg UPPDRAGSNUMMER: 2351240 ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING OCH UTREDNING FÖR DETALJPLAN SWECO CIVIL AB HALMSTAD GEOTEKNIK HANDLÄGGARE:
PM Geoteknik Österhagen
PM Geoteknik PM Geoteknik Datum 2017-02-19 Bakgrund Ett nytt bostadsområde planeras uppföras dels på tidigare uppfylld mark dels på jungfrulig mark. Den orörda marken planeras även den att få en uppfyllnad.
PM Geoteknik Skiljebo (Västerås 3:28) Västerås Stad
PM Geoteknik Skiljebo (Västerås 3:28) Västerås Stad Underlag för markplanering Projektnummer: 15045 Skapat av: Loxia Group Besöksadress: Järntorgsgatan 3, 703 61 Örebro www.loxiagroup.se Sida 2 av 6 Innehållsförteckning
KC, masstabilisering, solidifiering, ytstabilisering skillnaderna och användningsområden
KC, masstabilisering, solidifiering, ytstabilisering skillnaderna och användningsområden Stefan Larsson KTH Jordförstärkning vad menas? Förändring av jordens reologiska egenskaper, d.v.s. hållfasthets-,
PLANERAT EXPLOATERINGSOMRÅDE
Datum Sida 2013-03-11 1(5) GALOPPFÄLTET TÄBY PLANERAT EXPLOATERINGSOMRÅDE PM angående mark- och grundläggningsförhållanden underlag för detaljplan Uppdrag 1788 ULF JOHNSON GEO AB Karlbergsvägen 33, 113
PM/GEOTEKNIK - PLANERINGSUNDERLAG
SAMHÄLLSBYGGNADSKONTORET, LAHOLMS KOMMUN Mellbystrand Centrum, Laholm UPPDRAGSNUMMER: 2351262 ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING OCH UTREDNING FÖR DETALJPLAN SWECO CIVIL AB HALMSTAD GEOTEKNIK HANDLÄGGARE:
SYDÖSTRA KUMMELNÄS (OMRÅDE G)
NACKA KOMMUN SYDÖSTRA KUMMELNÄS (OMRÅDE G) Befintlig överbyggnad väg PM nr 2 Geoteknik. 2011-04-07 rev 110504 Beställare Nacka kommun Konsult WSP Samhällsbyggnad 121 88 Stockholm-Globen Besök: Arenavägen
Göteborgs Stad / Wallenstam AB Heden 24:12-14 Geoteknisk utredning för detaljplan
Göteborgs Stad / Wallenstam AB Göteborgs Stad / Wallenstam AB Beställare: Konsult: Uppdragsledare Handläggare Wallenstam AB (publ) Kungsportsavenyen 2 401 84 Göteborg Norconsult AB Box 8774 402 76 Göteborg
ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING
UPPLANDS-BRO KOMMUN KUNGSÄNGENS - TIBBLE 1:21 OCH 1:41 PLANERADE BOSTÄDER I GRÖNA DALEN ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING PM NR 1 BETR. MARK- OCH GRUNDLÄGGNINGSFÖRHÅLLANDEN PLANERINGSUNDERLAG Stockholm
Väg 163, Planerad GC väg i Grebbestad. PM Geoteknik. Datum:
Väg 163, Planerad GC väg i Grebbestad PM Geoteknik Datum:2009-06-26 Innehållsförteckning 1 Allmänt...3 2 Uppdragsbeskrivning...3 3. Underlag...3 4 Mark, vegetation och topografi...3 5 Geotekniska förhållanden...3
PM GEOTEKNIK FÖR DETALJPLAN
SAMHÄLLSBYGGNADSKONTORET, PARTILLE KOMMUN Kåhög 2:36 m.fl. detaljplan för förskola Geoteknisk undersökning Geoteknisk undersökning Uppdragsnummer: 2305 727 GÖTEBORG SWECO CIVIL AB GÖTEBORG GEOTEKNIK Sweco
Håby-Lycke 1:53 mfl, Munkedals kommun. PM Ändring av gällande detaljplan Geoteknik Upprättad av: Per Friberg Granskad av: Per Friberg
Håby-Lycke 1:53 mfl, Munkedals kommun Geoteknik 2013-06-16 Upprättad av: Per Friberg Granskad av: Per Friberg HÅBY-LYCKE 1:53 MFL, MUNKEDALS KOMMUN Geoteknik Kund Sjölyst Utveckling AS Konsult WSP Samhällsbyggnad
NACKA KOMMUN Neglinge 2:1, nybyggnad för handel. PM Geoteknik UNDERLAG FÖR DETALJPLAN 2012-09-02
NACKA KOMMUN Neglinge 2:1, nybyggnad för handel PM Geoteknik UNDERLAG FÖR DETALJPLAN 2012-09-02 Upprättat av: Hakan Güner Granskad av: Erik Westerberg Godkänd av: Anders Rydberg NACKA KOMMUN Neglinge 2:1,
PM Geoteknik. Upplands-Bro. Galoppbana. Projekteringsunderlag. Förhandskopia
Upplands-Bro Galoppbana Projekteringsunderlag Förhandskopia 2012-10-08 Galoppbana Upplands-Bro Datum Förhandskopia 2012-10-08 Uppdragsnummer 61191250147 Utgåva/Status Projekteringsunderlag Mats Oscarsson
Härryda kommun Landvetter centrum, Detaljplan Geoteknisk undersökning: PM beträffande geotekniska förhållanden
Beställare: Konsult: Uppdragsledare Handläggare 435 80 Mölnlycke Norconsult AB Box 8774 402 76 Göteborg Bengt Askmar Jimmy He Uppdragsnr: 03 2 82 Filnamn och sökväg: Kvalitetsgranskad av: Tryck: N:\03\2\03282\G\Beskr-PM-Eurokod\PM_Jh-Euro-
Översiktlig geoteknisk undersökning vid Risängen, Norrköpings kommun
PROJEKTERINGS PM Översiktlig geoteknisk undersökning vid, 2016-05-31 Upprättat av: Magnus Widfeldt Granskat av: Christina Berglund Godkänt av: Magnus Widfeldt PROJEKTERINGS PM Översiktlig geoteknisk undersökning
Dalvägen genom Dalkarlsängen Södra
Iterio AB Östgötagatan 12 116 25 Stockholm 08 410 363 00 info@iterio.se www.iterio.se Dalvägen genom Dalkarlsängen Södra PM Geoteknik Systemhandling Nacka kommun Uppdragsnummer: 4286 Datum: 2018-06-18
Baerum kommune. Geoteknisk rapport. Rud, Baerum kommune. Rapport nr Oppdragsnr.:
Baerum kommune Geoteknisk rapport Rud, Baerum kommune Rapport nr. 201 04 50-2 2012-11-19 Oppdragsnr.: 2010450 Dokument nr.2010450-2 00 2012-11-19 Geoteknisk rådgivning AMP BA BGE Rev. Dato: Beskrivelse
Tekniskt PM angående kompletterande undersökning för upprättande av detaljplan och stabilitetsutredning
PM Skanska Sverige AB 2012-02-07 Vår referens/nr 136931.050 DEL AV HJÄLTSGÅRD 6:1, SKEE STRÖMSTAD KOMMUN Tekniskt PM angående kompletterande undersökning för upprättande av detaljplan och stabilitetsutredning
Kämpersvik. Tanums kommun Detaljplan. Geoteknik. Utvärderingar, beräkningar och bedömningar PM ersätter PM och PM
Tel. 0522-946 50 Kämpersvik Tanums kommun Detaljplan Geoteknik Utvärderingar, beräkningar och bedömningar PM 2012-10-18 ersätter PM 2009-10-16 och PM 2010-05-25 Arb.nr U06030-1 Uddevalla 2012-10-18 Bohusgeo
Del av Kännestorp 2:25 Spekeröd, Stenungsunds kommun Detaljplan för förskola Geoteknik Utvärderingar och bedömningar PM Arb.
Del av Kännestorp 2:25 Spekeröd, Stenungsunds kommun Detaljplan för förskola Geoteknik Utvärderingar och bedömningar PM 2011-11-09 Arb.nr: U11086 Uddevalla 2011-11-09 Bohusgeo AB Bengt Leking Uppdragsansvarig
PM GEOTEKNIK SUNDSÄNGEN SYDNÄRKES BYGGFÖRVALTNING SWECO CIVIL AB HANDLÄGGARE VIKTOR KARLSSON GRANSKARE LARS MALMROS UPPDRAGSNUMMER
SYDNÄRKES BYGGFÖRVALTNING UPPDRAGSNUMMER 706 NORRKÖPING 08-07-06 SWECO CIVIL AB HANDLÄGGARE VIKTOR KARLSSON GRANSKARE LARS MALMROS (6) S w e co Hospitalsgatan B 607 Norrköping, Sverige www.sweco.se S we
STOCKHOLM STAD. Årstafältet Etapp 4 PM Geoteknik. Förhandskopia Upprättad av: Lars Henricsson
STOCKHOLM STAD Årstafältet Etapp 4 Förhandskopia 2016-04-27 Upprättad av: Lars Henricsson Årstafältet Etapp 4 Kund Stockholm Stad Exploateringskontoret Vello Parts Konsult WSP Samhällsbyggnad 121 88 Stockholm-Globen
ÖVERSIKTLIG GEOTEKNISK BEDÖMNING PRÄSTVIKEN-ERIKSBERG BOTKYRKA
PM ÖVERSIKTLIG GEOTEKNISK BEDÖMNING PRÄSTVIKEN-ERIKSBERG BOTKYRKA BILAGA TILL DETALJPLAN FÖR PRÄSTVIKEN 2014-11-17 Uppdrag: 251223, Stöd i framtagande av detaljplan Eriksberg, Botkyrka Titel på rapport:
WSP 1 018 5029 DEGERFORS KOMMUN PLANOMRÅDET VÄSTRA MÖCKELSTRANDEN. Geoteknisk undersökning. Örebro 2014-02-14
WSP 1 018 5029 DEGERFORS KOMMUN PLANOMRÅDET VÄSTRA MÖCKELSTRANDEN Geoteknisk undersökning Örebro WSP SAMHÄLLSBYGGNAD Box 8094 700 08 ÖREBRO Tel 0706 88 57 44 Handläggare: Jan-Eric Carlring WSP 1 018 5029
PM Östra Länken Etapp 4E
Handläggare Anders Andersson Tel +46405057110 Mobil +46703152590 E-post anders.andersson@afconsult.com Datum 2017-11-06 Projekt-ID 737193 ÖSTRA LÄNKEN ETAPP 4E UTREDNING OCH VAL AV ALTERNATIV PM Östra
DJUPSTABILISERING. NVF Förstärkningsseminar Mikko Leppänen / Ramboll Finland Oy
DJUPSTABILISERING NVF Förstärkningsseminar 20.3.2006 Mikko Leppänen / Ramboll Finland Oy Djupstabilisering Pelarstabilisering (KC-pelare) Masstabilisering (torvstabilisering) Stabilisering/solidifiering
KYRKEBY. Detaljplan. Göteborg Ärendenr. Handläggare i Göteborg AB. GEO-gruppen Hemsida:
STENUNGSUNDSS KOMMUN KYRKEBY 3:15 Detaljplan PM,, Geoteknik Göteborg Ärendenr. Handläggare 2017-10-19 17-210 David Scherman/Mattias Magnusson GEO-gruppen i Göteborg AB Marieholmsgatan 122 415 02 Göteborg
Rymdattacken 3 Linköping, Ullstämma. Projekterings PM Geoteknik (PMGeo) Botrygg Bygg AB. Uppdragsnummer: 10005597. Linköping 11 april 2012
Vårt datum 2012-04-11 Vår referens Geoteknik, Magnus Strömhag Uppdragsnummer 10005597 Rymdattacken 3 Linköping, Ullstämma Projekterings PM Geoteknik (PMGeo) Botrygg Bygg AB Uppdragsnummer: 10005597 Linköping
Laggkärlet 7, Linköping
HSB Produktion i Östergötland HB Linköping 2016-11-22 Datum 2016-11-22 Uppdragsnummer 1320022592 Märta Lidén Emma Backteman Lars Malmros Uppdragsledare Handläggare Granskare Ramböll Sverige AB Westmansgatan
Ale kommun. Älvängen, Starrkärr 4:10. Geoteknisk PM för detaljplan
Ale kommun Älvängen, Starrkärr 4:10 Geoteknisk PM för detaljplan 2013-08-14 ÅF-Infrastructure AB Kvarnbergsgatan 2, Box 1551 SE-401 51 Göteborg Telefon +46 10 505 00 00. Fax +46 10 505 30 09. Säte i Stockholm.
PM GEOTEKNIK. DPL Södertälje syd KILENKRYSSET BYGG AB UPPDRAGSNUMMER THOMAS REBLIN. repo001.docx
KILENKRYSSET BYGG AB DPL Södertälje syd UPPDRAGSNUMMER 3314821000 THOMAS REBLIN Sweco Södra Mariegatan 18 E Box 1902 SE 79119 Falun, Sverige Telefon +46 23 464 00 Fax +46 23 464 01 www.sweco.se Sweco Civil
Detaljerad stabilitetsutredning del av Kärna 67:1
Detaljerad stabilitetsutredning del av Kärna 67:1 Göteborg 2007-05-04 Rev. 1, 2007-05-29 Jonas Karlsson Tyréns AB Detaljerad stabilitetsutredning 2 (10) Innehållsförteckning 1 UPPDRAG... 3 2 PLANERAD BYGGNATION...
DETALJPLAN FÖR SÖRMARKEN, BANKBUDET 5, BORÅS STAD
DECEMBER 2017 BORÅS STAD DETALJPLAN FÖR SÖRMARKEN, BANKBUDET 5, BORÅS STAD ADRESS COWI AB Skärgårdsgatan 1 Box 12076 402 41 Göteborg TEL 010 850 10 00 FAX 010 850 10 10 WWW cowi.se DECEMBER 2017 BORÅS
DEL AV TORREBY 3:154 MUNKEDALS KOMMUN. Teknisk PM, Geoteknik. Slottet, Nybyggnation av bostadshus. Översiktlig geoteknisk utredning för detaljplan
DEL AV TORREBY 3:154 MUNKEDALS KOMMUN Slottet, Nybyggnation av bostadshus Översiktlig geoteknisk utredning för detaljplan Teknisk PM, Geoteknik Skanska Sverige AB Post 405 18 GÖTEBORG Besök Kilsgatan 4
Bergsvik delområde 4 Munkedals kommun Detaljplan Geoteknik Utvärderingar, beräkningar och bedömningar PM Arb.
Bergsvik delområde 4 Munkedals kommun Detaljplan Geoteknik Utvärderingar, beräkningar och bedömningar PM 2011-10-21 Arb.nr: U10064-4 Uddevalla 2011-10-21 Bohusgeo AB Bengt Leking Uppdragsansvarig bengt@bohusgeo.se
KARLSHAMNS KOMMUN Kungsparken, Mörrum Detaljplanen för del av Mörrum 73:1 & 73:4 m.fl. Översiktlig geoteknisk utredning
KARLSHAMNS KOMMUN 2015-09-30 Uppdragsnummer: 10216922 Upprättad av: Lars Marboe Granskad av: Evelina Nilsson KARLSHAMNS KOMMUN 73:4 m.fl. KUND Karlshamns kommun Anna Terning KONSULT WSP Samhällsbyggnad
PM GEOTEKNIK VÅRDBOENDE NÄVERTORP, KATRINEHOLM KFAB SWECO CIVIL AB HANDLÄGGARE VIKTOR KARLSSON GRANSKARE LARS MALMROS UPPDRAGSNUMMER
KFAB UPPDRAGSNUMMER 2181023 NORRKÖPING 2017-06-02 SWECO CIVIL AB HANDLÄGGARE VIKTOR KARLSSON GRANSKARE LARS MALMROS 1 (6) S w e co Luntgatan 28 SE-602 19 Norrköping, Sverige www.sweco.se S we c o Ci vi
PM GEOTEKNIK. VALLENTUNA KOMMUN Gärdesvägen, Vallentuna UPPDRAGSNUMMER GEOTEKNIK PLANERINGSUNDERLAG SWECO CIVIL AB STOCKHOLM GEOTEKNIK
VALLENTUNA KOMMUN Gärdesvägen, Vallentuna UPPDRAGSNUMMER 2177035 GEOTEKNIK Figur 1. Illustration: Reierstam arkitektur,www.vallentuna.se PLANERINGSUNDERLAG 2017-01-13 REVIDERAD 2017-02-07 REVIDERAD 2017-04-03
Skogsflyet, Norrköping
NCC Construction Sverige AB Linköping 2015-05-13 Datum 2015-05-13 Uppdragsnummer 1320014516 Märta Lidén Märta Lidén Lars Malmros Uppdragsledare Handläggare Granskare Ramböll Sverige AB Westmansgatan 47
Hövik 3:23. Projekterings-PM/Geoteknik. Höviksnäs, Tjörns kommun Släntstabilitetsutredning BOHUSGEO AB. Uppdragsansvarig: Henrik Lundström
BOHUSGEO AB Hövik 3:23 Höviksnäs, Tjörns kommun Släntstabilitetsutredning Projekterings- Uppdragsansvarig: Henrik Lundström Handläggare: Granskning: David Palmquist Henrik Lundström Uppdragsnr. 15061 Datum
Djupstabilisering i sulfidjord
Djupstabilisering i sulfidjord Träpålar har använts i ökande omfattning, Djupstabilisering kan vara ett intressant och kostnadseffektivt alternativ för jordförstärkning i sulfidjord. I flera tidigare fall
ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING
Datum Uppdragsnummer 2011-06-17 10 459 HALLSBERGS KOMMUN KOMMUNKANSLIET HALLSBERG RALA 1:19 o 13:2 M.FL. RALA INDUSTRIOMRÅDE ETAPP 3 ÖVERSIKTLIG GEOTEKNISK UNDERSÖKNING HALLSBERG RALA 1:19 OCH 13:2 M.FL.
PM Översiktlig geoteknisk bedömning TIERP 4:140. Tierps kommun 2014-04-11
PM Översiktlig geoteknisk bedömning TIERP 4:140 Tierps kommun 2014-04-11 Uppdrag: 253623, Buller, Risk, Geoteknik inför planläggning Titel på rapport: PM Översiktlig geoteknisk bedömning Status: Datum:
PM Geoteknik Geoteknisk förstudie för detaljplaneskede
PM Geoteknik Geoteknisk förstudie för detaljplaneskede Norrbacka 1:32-1:36 Sigtuna kommun www.bjerking.se Sida 2 (5) PM Geoteknik - Förutsättningar för projektering Uppdragsnamn Norrbacka Sigtuna kommun
Väg 222, tpl Kvarnholmen
Teknisk PM Geoteknik Väg 222, tpl Kvarnholmen Nacka kommun, Stockholms län 2014-10-31 Projektnummer: 107350 Dokumenttitel: Teknisk PM Geoteknik, Väg 222, tpl Kvarnholmen, Nacka kommun, Stockholms län Skapat
PM Geoteknik Lommarstranden
Handläggare Mikael Johansson Tel 010 505 04 42 Mobil 072 219 15 48 E-post mikael.a.johansson@afconsult.com Datum 2017-07-06 Projekt-ID 719324 Kund Norrtälje kommun Geoteknik Lommarstranden ÅF Infrastructure
RAPPORT SANERING JÄRNSÅGEN 3, TROLLHÄTTAN BEDÖMNING AV SÄTTNINGAR VID GRUNDVATTENSÄNKNING SWECO CIVIL PER LAGER. Sweco
1351995100 SANERING JÄRNSÅGEN 3, TROLLHÄTTAN BEDÖMNING AV SÄTTNINGAR VID GRUNDVATTENSÄNKNING SWECO CIVIL PER LAGER repo001.docx 2012-03-2914 Sweco repo001.docx 2012-03-2914 Sweco Rosenlundsgatan 4 Box
Väg 156, stigningsfält, Skoghem Backadal
TEKNISK PM GEOTEKNIK Väg 156, stigningsfält, Skoghem Backadal Marks kommun, Västra Götalands län Vägplan, 2018-05-07 Projektnummer: 157363 1 Trafikverket Postadress: 405 33 Göteborg E-post: trafikverket@trafikverket.se
PM Geoteknik DEL AV FÖRSTUDIE FÖR NORRA STADSOMRÅDET, LASSABACKA EKMARK LENA
Geoteknik DEL AV FÖRSTUDIE FÖR NORRA STADSOMRÅDET, LASSABACKA EKMARK LENA 2017-05-18 ÅF Infrastruktur AS, Grafiska vägen 2, SE-169 99 Göteborg Sweden Telefon +46 10 505 19 37, Säte i Göteborg, www.afconsult.com
Tekniskt PM Geoteknik. E20 förbi Vårgårda. Vårgårda kommun, Västra Götalands län. Vägplan: Projektnummer:150305
Tekniskt PM Geoteknik E20 förbi Vårgårda Vårgårda kommun, Västra Götalands län Vägplan: 2017-08-28 Projektnummer:150305 Trafikverket Postadress: Box 110, 541 23 Skövde E-post: trafikverket@trafikverket.se
Danderyds Kommun BRAGEHALLEN, ENEBYBERG. PROJEKTERINGS PM Grundläggningsrekommendationer. Uppdragsnummer: 40144. Stockholm 2015-10-21.
Danderyds Kommun BRAGEHALLEN, ENEBYBERG Uppdragsnummer: 40144 PROJEKTERINGS PM Grundläggningsrekommendationer Stockholm ELU Konsult AB Geoteknik, Stockholm Jimmie Andersson Handläggare Johan Olovsson Uppdragsledare
Göteborg Trollhättan (75 km) Nytt dubbelspår för 250 km/tim Ny fyrfältsväg med trafikplatser
Göteborg Trollhättan (75 km) Nytt dubbelspår för 250 km/tim Ny fyrfältsväg med trafikplatser Projektet i korthet Hela utbyggnaden mellan Göteborg och Trollhättan är ett samarbetsprojekt mellan Banverket
Ronneby kommun KV. KILEN RONNEBY
Geoteknisk PM KV. KILEN RONNEBY 2011-12-01 Dokumentinformation Objektnummer 108 451 Objektnamn KV. KILEN RONNEBY Filnamn Filtyp Programversion Projekteringssteg Statusbenämning Delområde Anläggningsdel
Kv Tjädern 17 Kungsbacka kommun Teknisk PM Geoteknik. Underlag för detaljplan
Beställare: Beställarens ombud: Konsult: Uppdragsledare Handläggare Skogsallen Fastighetsprojektering AB Carl-Johan Carlsson Norconsult AB Box 8774 402 76 Göteborg Bernhard Gervide-Eckel Araz Ismail Uppdragsnr:
1. Objekt och uppdrag. 2. Underlag. 3. Utförda undersökningar
Innehållsförteckning 1. Objekt och uppdrag... 3 2. Underlag... 3 3. Utförda undersökningar... 3 4. Befintliga förhållanden... 4 4.1. Allmänt... 4 4.2. Topografi... 4 4.3. Befintliga konstruktioner... 4
FÄRGELANDA KOMMUN DYRTOPR 1:3 M.FL (DEL AV) Detaljplan. Geoteknisk utredning
FÄRGELANDA KOMMUN DYRTOPR 1:3 M.FL (DEL AV) Detaljplan Geoteknisk utredning PM angående markförhållanden och bebyggelseförutsättningar Planeringsunderlag Göteborg 2011-05-10 Ärendenr. 10-169 Handläggare
BRILLINGE ÅTERVINNINGSCENTRAL, UPPSALA
PM Geoteknik (PM Geo) BRILLINGE ÅTERVINNINGSCENTRAL, UPPSALA 2017-06-08 Uppsala kommun, plan- och byggnadsnämnden. Dnr PBN 2015-000522, 2017-06-08 UPPDRAG 272040, Brillinge ÅVC Titel på rapport: PM Geoteknik,
Geotekniskt PM 1. Översiktlig geoteknisk undersökning för detaljplan. Gullbranna 1:13 mfl, Halmstads kommun 2014-04-04
Geotekniskt PM 1 2014-04-04 Upprättad av: Sayle Shamun Granskad av: Sven-Åke Öhman Godkänd av: Fredrik Stenfeldt GEOTEKNISKT PM 1 Kund Sindeman Byggnads AB Att: Jon E Sindeman Propellervägen 4 B 183 62
Häradsdomaren STOCKH OLMS STAD, ENSKEDE. Projekterings PM Geoteknik
STOCKH OLMS STAD, ENSKEDE Häradsdomaren Projekterings PM Geoteknik 2018-06 - 08 Google Eart h HÄRAD SD OM ARE N Projekterings PM Geoteknik KU N D Stockholms stad, Exploateringskontoret KON SU LT WSP Samhällsbyggnad
Väg E6 Helsingborg-Halmstad, Trafikplats Rebbelberga
GRANSKNINGSHANDLING Väg E6 Helsingborg-Halmstad, Trafikplats Rebbelberga Ängelholms kommun, Skåne län Tekniskt PM Geoteknik 2014-12-19 Dokument nr 1G07TP01 Projektnummer: V8850565 Yta för bild Trafikverket
KVASTMOSSEN, DJURHULT 1:5 M.FL. FASTIGHETER, NYBYGGNAD KOMBITERMINAL. Översiktlig geoteknisk utredning
KVASTMOSSEN, DJURHULT 1:5 M.FL. FASTIGHETER, NYBYGGNAD KOMBITERMINAL Översiktlig geoteknisk utredning 2016-10-28 KVASTMOSSEN, DJURHULT 1:5 M.FL. FASTIGHETER, NYBYGGNAD KOMBITERMINAL KUND Oskarshamns kommun
JAKOBSBERG 1:1 M.FL., KALMAR DETALJPLAN. Översiktlig geoteknisk utredning 2009-09-29. Upprättad av: Daniel Elm Granskad av: Torbjörn Johansson
JAKOBSBERG 1:1 M.FL., KALMAR DETALJPLAN Översiktlig geoteknisk utredning 2009-09-29 Upprättad av: Daniel Elm Granskad av: Torbjörn Johansson BESTÄLLARE Kalmar kommun, kommunledningskontoret KONSULT WSP
Kämpersvik Tanums kommun Detaljplan Geoteknik Utvärderingar, beräkningar och bedömningar PM ersätter PM Arb.
Tel. 0522-946 50 Kämpersvik Tanums kommun Detaljplan Geoteknik Utvärderingar, beräkningar och bedömningar PM 2007-06-12 ersätter PM 2006-06-12 Arb.nr U06030 Uddevalla 2007-06-12 Bohusgeo AB Bengt Leking
Geoteknisk PM Detaljplan
Geoteknisk PM Detaljplan Detaljplan Björnmossevägen Mellersta, Kälvesta, Stockholms Kommun Projekt nr: 18 13 76 2018-12-19 Geoteknisk PM Detaljplan Detaljplan Björnmossevägen Mellersta, Kälvesta, Stockholms
2007-01-04 10083754. Rev. A 2007-06-20. Stugsund, fd impregnering Söderhamns kommun. Geoteknisk undersökning. PM. Handläggare: Mats Granström
Stugsund, fd impregnering Söderhamns kommun Geoteknisk undersökning. PM Handläggare: Mats Granström WSP Samhällsbyggnad Norra Skeppargatan 11 803 20 Gävle Tel: 026-66 35 50 Fax: 026-66 35 60 WSP Sverige
PM Planeringsunderlag Geoteknik. Detaljplan för Kv Eol 2, Uddevalla 2014-08-13. Upprättad av: Charlotte Andersson Granskad av: Ulrika Isacsson
Geoteknik Detaljplan för Kv Eol 2, Uddevalla 2014-08-13 Upprättad av: Charlotte Andersson Granskad av: Ulrika Isacsson Geoteknik Detaljplan för Kv Eol 2, Uddevalla Kund Länsförsäkringar i Göteborg och
PLANERINGSUNDERLAG GEOTEKNIK
PLANERINGSUNDERLAG GEOTEKNIK MEJERIET 7, YSTADS KOMMUN UPPRÄTTAD: 2017-03-28 REVIDERAD: 2017-06-07 Upprättad av Granskad av Godkänd av Elisabeth Lindvall Fredrik Griwell Fredrik Griwell Innehållsförteckning
PLANERINGSUNDERLAG GEOTEKNIK
PLANERINGSUNDERLAG GEOTEKNIK KV LEKEN 1 M.FL., FALKENBERGS BOSTADS AB UPPRÄTTAD: Upprättad av Granskad av Godkänd av Magnus Palm Fredrik Griwell Magnus Palm Innehållsförteckning 1 Uppdrag...3 2 Underlag...4
TJÖRNS KOMMUN HÖVIKSNÄS. Geoteknisk utredning
TJÖRNS KOMMUN HÖVIKSNÄS Geoteknisk utredning PM angående markförhållanden och grundläggningsförutsättningar för planerade enbostadshus Projekteringsunderlag Göteborg 2008-07-04 Ärende nr. 08-069 Handläggare
Kungälv / BOKAB Tega 2:5, Detaljplan Geoteknisk undersökning: PM beträffande geotekniska förhålllanden
Geoteknisk undersökning: PM beträffande geotekniska förhålllanden Beställare: Konsult: Uppdragsledare Handläggare BOKAB UDDEVALLAVÄGEN 1 44230 KUNGÄLV Norconsult AB Box 8774 402 76 Göteborg Bengt Askmar
Linköpings Kommun. Norrberga 1:294 och del av Sturefors 1:4 inom norra Sturefors. Översiktlig geoteknisk undersökning.
1 Linköpings Kommun Norrberga 1:294 och del av Sturefors 1:4 inom norra Sturefors Översiktlig geoteknisk undersökning Geoteknisk PM Stadspartner AB Infrateknik/Geoteknik 2006-08 22 D nr 1161 2 Innehållsförteckning