E4 Sundsvall Sundsvallsbron
E4 Sundsvall LEVERANTÖRSDAG EN NY VÄG. 1000 2009 NYA MÖJLIGHETER One new road. 1000 new opportunities. Ove Malmberg, Assistant Project Manager 2 2014-10-10
Project E4 Sundsvall Total length: 20 km No of Bridges: 33 No of intersections: 5 Cost: 4600 MSEK Sundsvalls Bridge: 2109 m Free height: ca 33 m 3 2014-10-10
Four Contracts Three Contractors 4 2014-10-10
Contracts E4 Sundsvall Bridge. Contractor JVS (Max Bögl, STRABAG) Contract sum: 1 545 000 Mkr E4 - Myre Skönsmon. Contractor PEAB Contract sum : 1 096 000 Mkr E4 Skönsmon. Contractor Svevia. Contract sum : 31 000 Mkr E4 Skönsberg. Contractor Svevia. Contract sum: 156.785.Mkr 5 2014-10-10
Presentation General information Sundsvall Bridge Foundation Design Production and assembly Transport Questions 6 2014-10-10
Sundsvall Bridge Winner of an international architectural competition 1995 Lighting from below Four Lane Highway and a 4 meter wide part for pedestrian and bicycles Total weight of steel approx. 25 000 ton Free height 33 meter Sundsvall-bay is approx 10-15 meter deep 7 2014-10-10
Super structure Steel Box girder 8 2014-10-10
Generell Steel Section 9 2014-10-10
10 2014-10-10 Sheet Pile Foundation
EN NY VÄG. 1000 NYA MÖJLIGHETER Vatten Sediment och lösa lerlager Sand och morän Berg 11 2014-10-10
12 2014-10-10
13 2014-10-10
14 2014-10-10 EN NY VÄG. 1000 NYA MÖJLIGHETER
EN NY VÄG. 1000 NYA MÖJLIGHETER Vatten Sediment och lösa lerlager Sand och morän Berg 15 2014-10-10
16 2014-10-10
EN NY VÄG. 1000 NYA MÖJLIGHETER Vatten Sediment och lösa lerlager Sand och morän Berg 17 2014-10-10
18 2014-10-10
19 2014-10-10 EN NY VÄG. 1000 NYA MÖJLIGHETER
20 2014-10-10
EN NY VÄG. 1000 NYA MÖJLIGHETER Vatten Sediment och lösa lerlager Sand och morän Berg 21 2014-10-10
22 2014-10-10
23 2014-10-10
24 2014-10-10
25 2014-10-10 EN NY VÄG. 1000 NYA MÖJLIGHETER
EN NY VÄG. 1000 NYA MÖJLIGHETER Vatten Sediment och lösa lerlager Sand och morän Berg 26 2014-10-10
27 2014-10-10 EN NY VÄG. 1000 NYA MÖJLIGHETER
28 2014-10-10
29 2014-10-10
Principals of Sheet Pile Foundation Sheet piles with vertical load bearing capacity No slab action between bottom slab and sand fill. Accidental loads, Ship Impact, absorbed i sand fill. Forces between bottom slab and sheet piles transferred in shear studs. Approx 3000 shear studs per pier 30 2014-10-10
Advantages Principals of Sheet Pile Foundation Use of sheet pile anyway necassary for temporary works Robust design for accidental load capacity. Questions / Problems / Difficulties Requirements for controlls in production phase. Verification of load bearing capacity. Verification of sustainability (corrosion) 31 2014-10-10
Verification of load bearing capacity Before production Installation of test sheet piles Evaluation of load bearing capacity with CAP- WAP analysis Use of Dansk Rammeformel Resulted in a criteria for final blow of sheet piles Production sheet piles was installed according to the criteria. 32 2014-10-10
Controlls during production Controll av sand compaction Installation of inclinometers Measuring of geometrical entities Length Positions in plan Deflection Inclination Fulfilling of criteria for final blow 33 2014-10-10
Controlls after production Designers verification of the results from production New independent calculation based on the results from production 34 2014-10-10
Design is based on Verification of sustainability Corrosion 120 years life expectancy Maximum allowed corrosion over life-span No corrosion protection of sheet pile 35 2014-10-10
Verification of sustainability Corrosion Uncertainty of actual corrosion rate has led to Extra monitoring sheet pile installed A statistic modell for evaluation of allowed corrosion over time has been developed Monitoring sheet pile to be pulled up and investigated over the years to come. 36 2014-10-10
37 2014-10-10 Design
Geometry guidelines in separat design program 38 2014-10-10
11 bridge sections 9 in water area Sektion 1 Sektion 2 Sektion 3 Sektion 4 Sektion 5 Sektion 6 Sektion 7 Sektion 8 Sektion 9 Sektion 10 Sektion 11 39 2014-10-10
Steel segments and steel elements Element 40 2014-10-10
Typical steel section 41 2014-10-10
Stålelement Side elements 60 t Volume elements 100 t plate elements 35 t 42 2014-10-10 42
43 2014-10-10 Manufacturing and transport
44 2014-10-10
Transport Sundsvall Stettin Rotterdam Sengenthal / Bachhausen 45 2014-10-10
Juni 2013 Augusti 2013 September 2013 46 2014-10-10
47 2014-10-10 Steel erection in Sundsvall
48 2014-10-10
49 2014-10-10
50 2014-10-10
51 2014-10-10
Tack för visat intresse! Frågor? EN NY VÄG. 1000 NYA MÖJLIGHETER Ove Malmberg Biträdande projektledare E4 Sundsvall ove.malmberg@trafikverket.se Mobil: +46 (0)73-8034100 Trafikverket Ortviksvägen 2 856 33 Sundsvall www.trafikverket.se/e4sundsvall 52 2014-10-10