Hur Valmet hanterar risker i konstruktionsarbetet Peder Elden
Valmet Efter andra världskriget samlades ett antal statligt ägda verkstäder under namnet Valtion Metallitehtaat, 1951 fick företaget namnet Valmet Oy Valmet Oy har tillverkat fartyg, flygmaskiner, vapen, lok, traktorer, fartygsmaskiner, hissar, pappersmakiner, mm Under -80 och -90-talet stort fokus på pappersframställning med köp av bland annat KMW 1999 går Valmet och Rauma Corporation ihop och Metso Corporation bildas Valmet har varit vilande under en period men återstartas efter Metsos uppdelning -oktober 2013 Pannor kommer in i Metso, dec 2006, genom köp av AkerKvaerners panndel 2 24 April, 2014 Valmet Author / Title
Motala Verkstäder Jönköpings Mekaniska Verkstäder Maskinverken 1936 Götaverken Pannor 1994 Kvaerner Pulping Generator Kvaerner Power Recovery Boiler 1933 Metso Power Recovery Boiler Tampella 1996 Kvaerner Pulping
Complete Technology Solutions with Extensive Experience Pulping and recovery Paper, board and tissue making Energy Production Biotechnologies 200 wood handling systems 470 cooking systems 300 complete fiber lines 400 evaporation systems 350 recovery islands 900 paper machines 700 board machines 200 tissue machines 200 mechanical pulping lines 270 fluidized bed boilers 120 BioGrate boilers 400 environmental protection systems Gasification Pyrolysis LignoBoost Prehydrolysis of biomass 4 February 6 2014 Valmet
Tryckdelsammanställning 6 Date Author Title INTERNAL
Vilka skador uppstår på pannornas tryckkärl? De skador som inträffar idag är oftast sprickor korrosion extrema händelser Genom ett stort antal inspektioner har vi en god bild över skadeläget på pannor vilka vi har levererat 7 24 April, 2014 Valmet Author / Title
Sprickor Spänningskorrosionssprickor i en bottentub Ekonomiser 8 24 April, 2014 Valmet Author / Title
Sprickor Övergång alloy och kolstål Väggtub i ugnens nedre del 9 24 April, 2014 Valmet Author / Title
Korrosion Överhettartub Väggtub i nedre del av ugnen 10 24 April, 2014 Valmet Author / Title
Extrema händelser På följande bilder visas skador på en anläggning i Chile efter den svåra jordbävningen 2010 11 24 April, 2014 Valmet Author / Title
Chile, 27 feb 03:34 Location of seismic focus -35,826 / -72,669 115 km north-west of Concepcion 8.8 Richter scale Location of the mill 12 Date Author Title INTERNAL
Structural steel Top beam 13 Date Author Title INTERNAL
Wall tubes Location of damage in wall tube 14 Date Author Title INTERNAL
Dismantling and erection sequence Before start of dismantling of top steel the boiler is supported from below. Boiler mass is ~950 ton. The furnace wall panels shall take the total boiler weight, extra supports were needed Temporary support steel is installed below boiler and connected to existing columns Ten (10) supports are installed on the temporary support steel and connected to lower side wall headers at bottom beam supports The boiler is lifted by hydraulic jacks when top steel is ready. The hydraulic jacks are also connected to the bottom beam supports 15 Date Author Title INTERNAL
Calculation of wall panels First deformation mode of wall panels occurs above secondary air level Safety factor 3,01 16 Date Author Title INTERNAL
Hydraulic jack Bottom beam 17 Date Author Title INTERNAL
Top steel 18 Date Author Title INTERNAL
Transportation of economizer parts 19 Date Author Title INTERNAL
Allt projektarbete och alla inspektioner ger oss en stor erfarenhet vilken vi tar med oss in i riskanalysarbetet 20 24 April, 2014 Valmet Author / Title
Hur vi hanterar och analyserar risker Detta görs genom ett flertal steg, att vi arbetar i en projektorganisation påverkar givetvis detta arbete. Vi hanterar allt från nya anläggningar till mindre resevdelar Hjälp av ett program för de grundläggande säkerhetskraven enligt bilaga 1 I mindre projekt genomförs säkerhetsanalysen i konstruktionsgenomgången detta styrs genom inspektionsplanen Genom ett flertal möten där de olika disciplinerna träffas och diskuterar förutsättningarna 3834 möten (svets) Konstruktionsgenomgångar BAF möten (produktion) Montagegenomgångar 21 24 April, 2014 Valmet Author / Title
Riskanalysprogram 22 24 April, 2014 Valmet Author / Title
Kontrollplan 23 24 April, 2014 Valmet Author / Title
BAF - möten 24 24 April, 2014 Valmet Author / Title
3834 - möten 25 24 April, 2014 Valmet Author / Title
3834 - möten 26 24 April, 2014 Valmet Author / Title
EN-standarder EN 10216 o EN 10028 PWE EN 12952 Från en SA-kurs 1988 angående TKN 87 27 24 April, 2014 Valmet Author / Title
PWE 28 Date Author Title INTERNAL